Commercial Solar Power Generation

Autodesk solar installation
Autodesk solar installation

AUTODESK

System Description 80kW
Panels 320 JA Solar Tier one
Inverter 3 SOLAREDGE
Buildings 2

Installation completed in 2017 to provide cost savings. Fully monitored by Energy Assist.
The system was designed by Energy Assist and approved by Ausnet Services.
Design and approval timeframe 18 weeks
Installation timeframe 4 weeks

Autodesk solar installation
Autodesk solar installation

EDINBURGH COLLEGE

System Description 80kW
Panels 320 Jinko Solar Tier one
Inverter 4 ABB TRI Power
Buildings 4

Installation completed in 2016 to provide cost savings. Fully monitored by Energy Assist.
The system was designed by Energy Assist and approved by Ausnet Services.
Design and approval timeframe 10 weeks
Installation timeframe 4 weeks

Autodesk solar installation
Autodesk solar installation

OXLEY COLLEGE

System Description 467kW
Panels 1,868 Trina / Canadian Solar Tier one
Inverter 15 ABB TRI Power
Buildings 7

Installation completed in 2015 to provide cost savings. Fully monitored by Energy Assist. The system was designed by Energy Assist and approved by Ausnet Services.
Design and approval timeframe 16 weeks
Installation timeframe 10 weeks

Contact: – Graham Nelson 0413 279 408

Autodesk solar installation
Autodesk solar installation

ADVENTCARE Nursing Home

System Description 100kW
Panels 398 Jinko Solar Tier One
Inverter 15 ABB TRI Power
Buildings 7

Installation completed in 2015 to provide cost savings. Fully monitored by Energy Assist. The system was designed by Energy Assist and approved by Ausnet Services.
Design and approval timeframe 9 weeks
Installation timeframe 6 weeks

Contact: – Keith King 9259 2000

Autodesk solar installation
Autodesk solar installation

BMW DONCASTER

System Description 94kW
Panels 333 Canadian Solar Tier One
Inverter 3 SMA

Installation completed in 2016 to provide cost savings. Fully monitored by Energy Assist. The system was designed by Energy Assist and approved by United Energy.
Design and approval timeframe 11 weeks
Installation timeframe 6 weeks

Autodesk solar installation
Autodesk solar installation

PARAMOUNT AIR-CONDITIONING

System Description 29kW
Panels 109 Canadian Solar Tier One
Inverter 1 SolarEdge

Installation completed in 2016 to provide cost savings. Fully monitored by Energy Assist. The system was designed by Energy Assist and approved by United Energy.
Design and approval timeframe 5 weeks
Installation timeframe 1 week

Autodesk solar installation
Autodesk solar installation

RAVENSWOOD AUSTRALIA

System Description 29kW
Panels 105 Canadian Solar
Inverter 1 SMA TRI Power

Installation completed in 2017 to provide cost savings. Fully monitored by Energy Assist. The system was designed by Energy Assist and approved by Ausnet Services.
Design and approval timeframe 7 weeks
Installation timeframe 1 week

Arrow
Arrow
ArrowArrow
Slider
 

STCs and LGCs

Owners of a solar power system over 100kW are considered to be an electricity generator.  Under the Renewable Energy Target, in addition to STCs, power generators are also required to surrender a set number of Large-scale Generation Certificates (LGCs). LGCs can only be generated by commercial and utility-scale renewable energy generation systems (such as solar power systems) over 100kW in capacity that have undergone an accreditation process to produce them.

An important difference between STCs and LGCs is that LGCs are produced on an ongoing basis after the system is accredited, installed, and producing power. Large-scale generators therefore provide an ongoing revenue stream for their operators. As with STCs, an LGC is a tradable unit that acts as a currency for renewable energy, and prices therefore fluctuate with supply and demand.